Public space
Under construction
Cementerio Histórico de San Miguel · repaving, lighting and drainage (phase 1)
- Builder
- Rofez Construcciones S.L.
- Public body
- Ayuntamiento de Málaga, Parcemasa
- Start
- 31 Jul 2026
- Budget
- €2.63M
Record updated: 7 Nov 2026. Data from official sources.
Works started on 31 July 2026; temporary entrance from Calle Molino de San Telmo since 9 November 2026
Hand-reviewed major project. The timeline summarises public sources; the link is the latest source checked.
Phase 1 renews the paving of all paths in the pre-19th-century-extension part of the cemetery, keeping early 20th-century tiles where possible, and installs new ornamental lighting and a new rainwater network, under archaeological supervision. A second phase will extend the works to the whole cemetery. Part of the Conecta_Málaga plan, co-funded by the EU's ERDF (FEDER) 2021-2027 programme.
Timeline
- Parcemasa puts the works out to tender (€2,630,701.23 incl. VAT, 10 months) · source
- Contract signed with Rofez Construcciones, S.L. for €2,564,745.40, 10 months · source
- Works started · source
- Main gate on Plaza del Patrocinio closed: temporary entrance from Calle Molino de San Telmo from 9 November for about five months · source
Change history
- Planned start: from “not stated” to “31 Jul 2026”
- Investment: from “not stated” to “€2.56M”
- Tender: from “not stated” to “€2.63M”