Public space
Under construction
Calle Lagunillas, Plaza de la Victoria side and Plaza Miguel de los Reyes · renewal phase 2
- Builder
- Construcciones Lasor S.L.
- Public body
- Ayuntamiento de Málaga
- Budget
- €2.71M
Record updated: 14 Jul 2026. Data from official sources.
Awarded in June 2025; on 14 July 2026 the city described it as about to be completed. We have not yet seen a completion notice
Hand-reviewed major project. The timeline summarises public sources; the link is the latest source checked.
Calle Lagunillas becomes a Zone 20 single-level street like Calle Carretería; its last stretch and the side of Plaza de la Victoria are pedestrianised, and Plaza Miguel de los Reyes gets a play area and the relocated sculpture. Paving, sewer, water, lighting and overhead cables are renewed. Part of the Conecta_Málaga plan, co-funded by the EU's ERDF (FEDER) 2021-2027 programme.
Timeline
- Works put out to tender (€2,707,759.60 incl. VAT, 12 months) · source
- Awarded to Construcciones Lasor S.L. for €2,460,648.82 (VAT incl.), 12 months · source
- The city reports a high degree of execution · source
- The city says the Lagunillas renewal is about to be completed · source
Change history
No changes recorded since we first saw it (12 Nov 2026).